What the rules make a plant keep

Maintenance record retention requirements in the US and GB

Updated

Safety and environmental rules on both sides of the Atlantic already make a plant record its inspections, examinations, tests and leak repairs. Some set a period, many tie the record to the next inspection or to the life of the equipment, and several set no period at all. These are the texts we read, in their own words.

Describe our work orders

US federal rules

Process safety: every inspection and test documented

OSHA 29 CFR 1910.119(j) says: "The employer shall document each inspection and test that has been performed on process equipment." EPA's risk management rule, 40 CFR 68.73, puts the same duty on "the owner or operator".

Source: eCFR, 29 CFR 1910.119

Refrigerant appliances: three years

EPA's 40 CFR 82.157 says: "All records identified in this paragraph must be kept for at least three years in electronic or paper format, unless otherwise specified."

Source: eCFR, 40 CFR 82.157

Overhead cranes: a monthly certification record

OSHA 29 CFR 1910.179 calls for a monthly hook and chain inspection "with a certification record which includes the date of inspection, the signature of the person who performed the inspection and the serial number, or other identifier, of the hook inspected."

Source: eCFR, 29 CFR 1910.179

GB regulations

PUWER: kept until the next inspection

Regulation 6(3) of PUWER 1998 says: "Every employer shall ensure that the result of an inspection made under this regulation is recorded and kept until the next inspection under this regulation is recorded."

Source: PUWER 1998, regulation 6

LOLER: two years for a lifting accessory

LOLER 1998 regulation 11 keeps a thorough examination report on a lifting accessory "for two years after the report is made", and on other lifting equipment "until he ceases to use the lifting equipment".

Source: LOLER 1998, regulation 11

Pressure systems: the last report

Regulation 14 of the Pressure Systems Safety Regulations 2000 says the user of an installed system and the owner of a mobile one shall keep "the last report relating to the system made by the competent person pursuant to regulation 9(3)".

Source: Pressure Systems Safety Regulations 2000, regulation 14

F-gas leak checks: five years

Article 6 of the retained F-gas Regulation says operators "shall keep the records referred to in that paragraph for at least five years".

Source: Regulation (EU) 517/2014 as retained, article 6

Keeping and licensing are separate questions

A rule that makes a plant keep a record does not stop it licensing a copy, and it does not make the copy free of personal data or of a customer's confidential information. Keep the originals the rules require, and license a cleaned copy. These are the texts as read, not legal advice.

Tell us what the plant's maintenance system holds

No typing, only taps. At the end you see what your answers mean and what we do next.

Question 1 of 4

Which maintenance records could the plant license?

Rather write it down?

Rather write it down?

Tell us what the plant's maintenance system holds

The plant's own maintenance records
  • We never ask for technicians' names
  • Your CMMS vendor's terms named in the outline

Ten years of closed work orders in the CMMS?

Tell us which maintenance system holds them, how many assets and years it covers, and whether inspection certificates sit beside them, and we reply by email.

Sources

This site's own datasets, every figure quoted from its source and dated:

  1. Legal
  2. Privacy Statement
  3. Privacy Policy
  4. Terms and Conditions of Fracttal CMMS
  5. How to Transform Your Sleep Journey in Australia
  6. Privacy Policy
  7. Privacy Statement
  8. Global Privacy Policy
Describe our work orders