# What the law makes a plant record about its equipment

> 2 of 13 equipment record rules read fix a period for keeping the record, newest read 8 November 2026.

Sell Maintenance Data to AI · https://sellmaintenancedatatoai.com/datasets/maintenance-records-law/ · computed 2026-11-08

**Rules that set a fixed period:** 2 of 13 rules (13 texts read; 16 named).

## The answers, question by question

- **What must be recorded:** the result of an inspection, examination or test 9, refrigerant or gas leak checks and repairs 2, a written procedure, scheme or certification 1, a maintenance log or record of repairs 1
- **Whose duty it is:** the employer 7, the owner, user or operator of the equipment or process 4, not stated 1, the competent person who examines it 1
- **How long the record is kept:** no period set in the text 8, until the next inspection, or for the life of the equipment 3, a fixed period stated in the text 2
- **The rule, in its own words:** stated 13

## Every rule

| Rule | What must be recorded | Whose duty it is | How long the record is kept | The rule, in its own words |
|---|---|---|---|---|
| 29 CFR 1910.119(j), process safety mechanical integrity (OSHA) | the result of an inspection, examination or test | the employer | no period set in the text | The employer shall document each inspection and test that has been performed on process… |
| 29 CFR 1910.147, lockout and tagout (OSHA) | the result of an inspection, examination or test | the employer | no period set in the text | The certification shall identify the machine or equipment on which the energy control… |
| 29 CFR 1910.178, powered industrial trucks (OSHA) | a written procedure, scheme or certification | the employer | no period set in the text | If at any time a powered industrial truck is found to be in need of repair, defective, or… |
| 29 CFR 1910.179, overhead and gantry cranes (OSHA) | the result of an inspection, examination or test | not stated | no period set in the text | Visual inspection daily; monthly inspection with a certification record which includes… |
| 40 CFR 68.73, risk management mechanical integrity (EPA) | the result of an inspection, examination or test | the owner, user or operator of the equipment or process | no period set in the text | The owner or operator shall establish and implement written procedures to maintain the… |
| 40 CFR 82.157, appliance maintenance and leak repair (EPA) | refrigerant or gas leak checks and repairs | the owner, user or operator of the equipment or process | a fixed period stated in the text | Owners or operators must maintain a record including the following information for each… |
| LOLER 1998 regulation 11, keeping of information (GB) | the result of an inspection, examination or test | the employer | until the next inspection, or for the life of the equipment | in the case of a thorough examination under paragraph (1) of regulation 9 of an accessory… |
| LOLER 1998 regulation 9, thorough examination and inspection (GB) | the result of an inspection, examination or test | the employer | no period set in the text | if appropriate for the purpose, is inspected by a competent person at suitable intervals… |
| PSSR 2000 regulation 14, keeping of records (GB) | the result of an inspection, examination or test | the owner, user or operator of the equipment or process | until the next inspection, or for the life of the equipment | Where the user or owner of a pressure system or part thereof changes, the previous user… |
| PSSR 2000 regulation 9, examination under the written scheme (GB) | the result of an inspection, examination or test | the competent person who examines it | no period set in the text | within 28 days of the completion of the examination (or, in the case of integrated… |
| PUWER 1998 regulation 5, maintenance (GB) | a maintenance log or record of repairs | the employer | no period set in the text | Every employer shall ensure that work equipment is maintained in an efficient state, in… |
| PUWER 1998 regulation 6, inspection (GB) | the result of an inspection, examination or test | the employer | until the next inspection, or for the life of the equipment | Every employer shall ensure that the result of an inspection made under this regulation… |
| Retained F-gas Regulation (EU) 517/2014, article 6 (GB) | refrigerant or gas leak checks and repairs | the owner, user or operator of the equipment or process | a fixed period stated in the text | the operators referred to in paragraph 1 shall keep the records referred to in that… |

## The sentence each answer rests on (52)

- 29 CFR 1910.119(j), process safety mechanical integrity (OSHA), [eCFR 29 CFR 1910.119](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119), read 2026-11-06, What must be recorded: "The employer shall document each inspection and test that has been performed on process equipment."
- 29 CFR 1910.119(j), process safety mechanical integrity (OSHA), [eCFR 29 CFR 1910.119](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119), read 2026-11-06, Whose duty it is: "The employer shall document each inspection and test that has been performed on process equipment."
- 29 CFR 1910.119(j), process safety mechanical integrity (OSHA), [eCFR 29 CFR 1910.119](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119), read 2026-11-06, How long the record is kept: "The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed"
- 29 CFR 1910.119(j), process safety mechanical integrity (OSHA), [eCFR 29 CFR 1910.119](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119), read 2026-11-06, The rule, in its own words: "The employer shall document each inspection and test that has been performed on process equipment."
- 29 CFR 1910.147, lockout and tagout (OSHA), [eCFR 29 CFR 1910.147](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-J/section-1910.147), read 2026-11-02, What must be recorded: "The employer shall certify that the periodic inspections have been performed."
- 29 CFR 1910.147, lockout and tagout (OSHA), [eCFR 29 CFR 1910.147](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-J/section-1910.147), read 2026-11-02, Whose duty it is: "The employer shall certify that the periodic inspections have been performed."
- 29 CFR 1910.147, lockout and tagout (OSHA), [eCFR 29 CFR 1910.147](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-J/section-1910.147), read 2026-11-02, How long the record is kept: "The certification shall identify the machine or equipment on which the energy control procedure was being utilized, the date of the inspection, the employees included in the inspection, and the person performing the inspection."
- 29 CFR 1910.147, lockout and tagout (OSHA), [eCFR 29 CFR 1910.147](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-J/section-1910.147), read 2026-11-02, The rule, in its own words: "The certification shall identify the machine or equipment on which the energy control procedure was being utilized, the date of the inspection, the employees included in the inspection, and the person performing the inspection."
- 29 CFR 1910.178, powered industrial trucks (OSHA), [eCFR 29 CFR 1910.178](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.178), read 2026-10-31, What must be recorded: "The employer shall certify that each operator has been trained and evaluated as required by this paragraph (l)."
- 29 CFR 1910.178, powered industrial trucks (OSHA), [eCFR 29 CFR 1910.178](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.178), read 2026-10-31, Whose duty it is: "The employer shall certify that each operator has been trained and evaluated as required by this paragraph (l)."
- 29 CFR 1910.178, powered industrial trucks (OSHA), [eCFR 29 CFR 1910.178](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.178), read 2026-10-31, How long the record is kept: "The certification shall include the name of the operator, the date of the training, the date of the evaluation, and the identity of the person(s) performing the training or evaluation."
- 29 CFR 1910.178, powered industrial trucks (OSHA), [eCFR 29 CFR 1910.178](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.178), read 2026-10-31, The rule, in its own words: "If at any time a powered industrial truck is found to be in need of repair, defective, or in any way unsafe, the truck shall be taken out of service until it has been restored to safe operating condition."
- 29 CFR 1910.179, overhead and gantry cranes (OSHA), [eCFR 29 CFR 1910.179](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.179), read 2026-11-02, What must be recorded: "A thorough inspection of all ropes shall be made at least once a month and a certification record which includes the date of inspection, the signature of the person who performed the inspection and an identifier for the ropes which were inspected shall be kept on file where readily available to appointed personnel."
- 29 CFR 1910.179, overhead and gantry cranes (OSHA), [eCFR 29 CFR 1910.179](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.179), read 2026-11-02, Whose duty it is: Nothing on this text answers it (41,804 characters of text text, read 2026-11-02).
- 29 CFR 1910.179, overhead and gantry cranes (OSHA), [eCFR 29 CFR 1910.179](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.179), read 2026-11-02, How long the record is kept: "A thorough inspection of all ropes shall be made at least once a month and a certification record which includes the date of inspection, the signature of the person who performed the inspection and an identifier for the ropes which were inspected shall be kept on file where readily available to appointed personnel."
- 29 CFR 1910.179, overhead and gantry cranes (OSHA), [eCFR 29 CFR 1910.179](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.179), read 2026-11-02, The rule, in its own words: "Visual inspection daily; monthly inspection with a certification record which includes the date of inspection, the signature of the person who performed the inspection and the serial number, or other identifier, of the hook inspected."
- 40 CFR 68.73, risk management mechanical integrity (EPA), [eCFR 40 CFR 68.73](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D/section-68.73), read 2026-11-01, What must be recorded: "The owner or operator shall document each inspection and test that has been performed on process equipment."
- 40 CFR 68.73, risk management mechanical integrity (EPA), [eCFR 40 CFR 68.73](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D/section-68.73), read 2026-11-01, Whose duty it is: "The owner or operator shall document each inspection and test that has been performed on process equipment."
- 40 CFR 68.73, risk management mechanical integrity (EPA), [eCFR 40 CFR 68.73](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D/section-68.73), read 2026-11-01, How long the record is kept: "The documentation shall identify the date of the inspection or test, the name of the person who performed the inspection or test, the serial number or other identifier of the equipment on which the inspection or test was performed, a description of the inspection or test performed"
- 40 CFR 68.73, risk management mechanical integrity (EPA), [eCFR 40 CFR 68.73](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D/section-68.73), read 2026-11-01, The rule, in its own words: "The owner or operator shall establish and implement written procedures to maintain the on-going integrity of process equipment."
- 40 CFR 82.157, appliance maintenance and leak repair (EPA), [eCFR 40 CFR 82.157](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-82/subpart-F/section-82.157), read 2026-10-26, What must be recorded: "Owners or operators must maintain records of the dates and results of all initial and follow-up verification tests."
- 40 CFR 82.157, appliance maintenance and leak repair (EPA), [eCFR 40 CFR 82.157](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-82/subpart-F/section-82.157), read 2026-10-26, Whose duty it is: "Owners or operators must maintain a record including the following information for each time an appliance with a full charge of 50 or more pounds is maintained, serviced, repaired, or disposed of, when applicable."
- 40 CFR 82.157, appliance maintenance and leak repair (EPA), [eCFR 40 CFR 82.157](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-82/subpart-F/section-82.157), read 2026-10-26, How long the record is kept: "All records identified in this paragraph must be kept for at least three years in electronic or paper format, unless otherwise specified."
- 40 CFR 82.157, appliance maintenance and leak repair (EPA), [eCFR 40 CFR 82.157](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-82/subpart-F/section-82.157), read 2026-10-26, The rule, in its own words: "Owners or operators must maintain a record including the following information for each time an appliance with a full charge of 50 or more pounds is maintained, serviced, repaired, or disposed of, when applicable."
- LOLER 1998 regulation 11, keeping of information (GB), [legislation.gov.uk, SI 1998/2307 regulation 11](https://www.legislation.gov.uk/uksi/1998/2307/regulation/11), read 2026-11-07, What must be recorded: "every report made to him under regulation 10(1)(b) is kept available for inspection"
- LOLER 1998 regulation 11, keeping of information (GB), [legislation.gov.uk, SI 1998/2307 regulation 11](https://www.legislation.gov.uk/uksi/1998/2307/regulation/11), read 2026-11-07, Whose duty it is: "The employer shall ensure that the information contained in"
- LOLER 1998 regulation 11, keeping of information (GB), [legislation.gov.uk, SI 1998/2307 regulation 11](https://www.legislation.gov.uk/uksi/1998/2307/regulation/11), read 2026-11-07, How long the record is kept: "in the case of a thorough examination under paragraph (1) of regulation 9 of lifting equipment other than an accessory for lifting, until he ceases to use the lifting equipment;"
- LOLER 1998 regulation 11, keeping of information (GB), [legislation.gov.uk, SI 1998/2307 regulation 11](https://www.legislation.gov.uk/uksi/1998/2307/regulation/11), read 2026-11-07, The rule, in its own words: "in the case of a thorough examination under paragraph (1) of regulation 9 of an accessory for lifting, for two years after the report is made;"
- LOLER 1998 regulation 9, thorough examination and inspection (GB), [legislation.gov.uk, SI 1998/2307 regulation 9](https://www.legislation.gov.uk/uksi/1998/2307/regulation/9), read 2026-11-07, What must be recorded: "unless it is accompanied by physical evidence that the last thorough examination required to be carried out under this regulation has been carried out."
- LOLER 1998 regulation 9, thorough examination and inspection (GB), [legislation.gov.uk, SI 1998/2307 regulation 9](https://www.legislation.gov.uk/uksi/1998/2307/regulation/9), read 2026-11-07, Whose duty it is: "Every employer shall ensure that before lifting equipment is put into service for the first time by him it is thoroughly examined for any defect unless either"
- LOLER 1998 regulation 9, thorough examination and inspection (GB), [legislation.gov.uk, SI 1998/2307 regulation 9](https://www.legislation.gov.uk/uksi/1998/2307/regulation/9), read 2026-11-07, How long the record is kept: "unless it is accompanied by physical evidence that the last thorough examination required to be carried out under this regulation has been carried out."
- LOLER 1998 regulation 9, thorough examination and inspection (GB), [legislation.gov.uk, SI 1998/2307 regulation 9](https://www.legislation.gov.uk/uksi/1998/2307/regulation/9), read 2026-11-07, The rule, in its own words: "if appropriate for the purpose, is inspected by a competent person at suitable intervals between thorough examinations,"
- PSSR 2000 regulation 14, keeping of records (GB), [legislation.gov.uk, SI 2000/128 regulation 14](https://www.legislation.gov.uk/uksi/2000/128/regulation/14), read 2026-11-01, What must be recorded: "the last report relating to the system made by the competent person pursuant to regulation 9(3);"
- PSSR 2000 regulation 14, keeping of records (GB), [legislation.gov.uk, SI 2000/128 regulation 14](https://www.legislation.gov.uk/uksi/2000/128/regulation/14), read 2026-11-01, Whose duty it is: "The user of an installed system and the owner of a mobile system shall keep"
- PSSR 2000 regulation 14, keeping of records (GB), [legislation.gov.uk, SI 2000/128 regulation 14](https://www.legislation.gov.uk/uksi/2000/128/regulation/14), read 2026-11-01, How long the record is kept: "until a further examination has been carried out since that agreement or notification under the scheme of examination."
- PSSR 2000 regulation 14, keeping of records (GB), [legislation.gov.uk, SI 2000/128 regulation 14](https://www.legislation.gov.uk/uksi/2000/128/regulation/14), read 2026-11-01, The rule, in its own words: "Where the user or owner of a pressure system or part thereof changes, the previous user or owner shall as soon as is practicable give to the new user or owner in writing anything (relating to the system or part thereof, as the case may be) kept by him under this regulation."
- PSSR 2000 regulation 9, examination under the written scheme (GB), [legislation.gov.uk, SI 2000/128 regulation 9](https://www.legislation.gov.uk/uksi/2000/128/regulation/9), read 2026-11-01, What must be recorded: "state which parts of the pressure system have been examined, the condition of those parts and the results of the examination;"
- PSSR 2000 regulation 9, examination under the written scheme (GB), [legislation.gov.uk, SI 2000/128 regulation 9](https://www.legislation.gov.uk/uksi/2000/128/regulation/9), read 2026-11-01, Whose duty it is: "make a written report of the examination, sign it or add his name to it, date it and send it to the user (in the case of an installed system) or owner (in the case of a mobile system)"
- PSSR 2000 regulation 9, examination under the written scheme (GB), [legislation.gov.uk, SI 2000/128 regulation 9](https://www.legislation.gov.uk/uksi/2000/128/regulation/9), read 2026-11-01, How long the record is kept: "make a written report of the examination, sign it or add his name to it, date it and send it to the user (in the case of an installed system) or owner (in the case of a mobile system)"
- PSSR 2000 regulation 9, examination under the written scheme (GB), [legislation.gov.uk, SI 2000/128 regulation 9](https://www.legislation.gov.uk/uksi/2000/128/regulation/9), read 2026-11-01, The rule, in its own words: "within 28 days of the completion of the examination (or, in the case of integrated installed systems where the examination is part of a series, within 28 days of the completion of the last examination in that series); or"
- PUWER 1998 regulation 5, maintenance (GB), [legislation.gov.uk, SI 1998/2306 regulation 5](https://www.legislation.gov.uk/uksi/1998/2306/regulation/5), read 2026-10-31, What must be recorded: "Every employer shall ensure that where any machinery has a maintenance log, the log is kept up to date."
- PUWER 1998 regulation 5, maintenance (GB), [legislation.gov.uk, SI 1998/2306 regulation 5](https://www.legislation.gov.uk/uksi/1998/2306/regulation/5), read 2026-10-31, Whose duty it is: "Every employer shall ensure that where any machinery has a maintenance log, the log is kept up to date."
- PUWER 1998 regulation 5, maintenance (GB), [legislation.gov.uk, SI 1998/2306 regulation 5](https://www.legislation.gov.uk/uksi/1998/2306/regulation/5), read 2026-10-31, How long the record is kept: "Every employer shall ensure that where any machinery has a maintenance log, the log is kept up to date."
- PUWER 1998 regulation 5, maintenance (GB), [legislation.gov.uk, SI 1998/2306 regulation 5](https://www.legislation.gov.uk/uksi/1998/2306/regulation/5), read 2026-10-31, The rule, in its own words: "Every employer shall ensure that work equipment is maintained in an efficient state, in efficient working order and in good repair."
- PUWER 1998 regulation 6, inspection (GB), [legislation.gov.uk, SI 1998/2306 regulation 6](https://www.legislation.gov.uk/uksi/1998/2306/regulation/6), read 2026-11-08, What must be recorded: "Every employer shall ensure that the result of an inspection made under this regulation is recorded and kept until the next inspection under this regulation is recorded."
- PUWER 1998 regulation 6, inspection (GB), [legislation.gov.uk, SI 1998/2306 regulation 6](https://www.legislation.gov.uk/uksi/1998/2306/regulation/6), read 2026-11-08, Whose duty it is: "Every employer shall ensure that the result of an inspection made under this regulation is recorded and kept until the next inspection under this regulation is recorded."
- PUWER 1998 regulation 6, inspection (GB), [legislation.gov.uk, SI 1998/2306 regulation 6](https://www.legislation.gov.uk/uksi/1998/2306/regulation/6), read 2026-11-08, How long the record is kept: "Every employer shall ensure that the result of an inspection made under this regulation is recorded and kept until the next inspection under this regulation is recorded."
- PUWER 1998 regulation 6, inspection (GB), [legislation.gov.uk, SI 1998/2306 regulation 6](https://www.legislation.gov.uk/uksi/1998/2306/regulation/6), read 2026-11-08, The rule, in its own words: "Every employer shall ensure that the result of an inspection made under this regulation is recorded and kept until the next inspection under this regulation is recorded."
- Retained F-gas Regulation (EU) 517/2014, article 6 (GB), [legislation.gov.uk, Regulation (EU) 517/2014 article 6](https://www.legislation.gov.uk/eur/2014/517/article/6), read 2026-10-28, What must be recorded: "Operators of equipment which is required to be checked for leaks pursuant to Article 4(1), shall establish and maintain records for each piece of such equipment specifying the following information:"
- Retained F-gas Regulation (EU) 517/2014, article 6 (GB), [legislation.gov.uk, Regulation (EU) 517/2014 article 6](https://www.legislation.gov.uk/eur/2014/517/article/6), read 2026-10-28, Whose duty it is: "Operators of equipment which is required to be checked for leaks pursuant to Article 4(1), shall establish and maintain records for each piece of such equipment specifying the following information:"
- Retained F-gas Regulation (EU) 517/2014, article 6 (GB), [legislation.gov.uk, Regulation (EU) 517/2014 article 6](https://www.legislation.gov.uk/eur/2014/517/article/6), read 2026-10-28, How long the record is kept: "the operators referred to in paragraph 1 shall keep the records referred to in that paragraph for at least five years;"
- Retained F-gas Regulation (EU) 517/2014, article 6 (GB), [legislation.gov.uk, Regulation (EU) 517/2014 article 6](https://www.legislation.gov.uk/eur/2014/517/article/6), read 2026-10-28, The rule, in its own words: "the operators referred to in paragraph 1 shall keep the records referred to in that paragraph for at least five years;"

## Read and set aside

- [The Electricity at Work Regulations 1989](https://www.legislation.gov.uk/uksi/1989/635/regulation/4): EAWR 1989 regulation 4 requires electrical systems to be maintained but sets no record in its text
- [Provision and Use of Work Equipment Regulations 1998 (PUWER)](https://www.hse.gov.uk/work-equipment-machinery/puwer.htm): HSE's PUWER page is an index of links to its guidance; it states no rule itself
- [Lifting Operations and Lifting Equipment Regulations (LOLER)](https://www.hse.gov.uk/work-equipment-machinery/loler.htm): HSE's LOLER page is an index of links to its guidance; it states no rule itself

## Methodology

We read each rule's eCFR, legislation.gov.uk and HSE texts on equipment maintenance and inspection records through our own reader and stored every text in full, with a sha256 hash on each row. Every text was read for four questions, each answer taken from its own words: what must be recorded, whose duty it is, how long the record is kept, the rule, in its own words. A stated answer always carries its sentence, checked against what was stored. Where it says 'not stated', the text does not address the question; 'varies' means a rule's texts give different answers. Read: 13 rules, 13 texts.

## Sources

- [eCFR :: 40 CFR 82.157 -- Appliance maintenance and leak repair.](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-82/subpart-F/section-82.157) (read)
- [Regulation (EU) No 517/2014 of the European Parliament and of the Council of 16 April 2014](https://www.legislation.gov.uk/eur/2014/517/article/6) (read)
- [eCFR :: 29 CFR 1910.147 -- The control of hazardous energy (lockout/tagout).](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-J/section-1910.147) (read)
- [eCFR :: 29 CFR 1910.179 -- Overhead and gantry cranes.](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.179) (read)
- [eCFR :: 29 CFR 1910.119 -- Process safety management of highly hazardous chemicals.](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119) (read)
- [eCFR :: 29 CFR 1910.178 -- Powered industrial trucks.](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-N/section-1910.178) (read)
- [eCFR :: 40 CFR 68.73 -- Mechanical integrity.](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D/section-68.73) (read)
- [The Provision and Use of Work Equipment Regulations 1998](https://www.legislation.gov.uk/uksi/1998/2306/regulation/5) (read)
- [The Provision and Use of Work Equipment Regulations 1998](https://www.legislation.gov.uk/uksi/1998/2306/regulation/6) (read)
- [The Lifting Operations and Lifting Equipment Regulations 1998](https://www.legislation.gov.uk/uksi/1998/2307/regulation/11) (read)
- [The Lifting Operations and Lifting Equipment Regulations 1998](https://www.legislation.gov.uk/uksi/1998/2307/regulation/9) (read)
- [The Pressure Systems Safety Regulations 2000](https://www.legislation.gov.uk/uksi/2000/128/regulation/14) (read)
- [The Electricity at Work Regulations 1989](https://www.legislation.gov.uk/uksi/1989/635/regulation/4) (not-terms)
- [The Pressure Systems Safety Regulations 2000](https://www.legislation.gov.uk/uksi/2000/128/regulation/9) (read)
- [Provision and Use of Work Equipment Regulations 1998 (PUWER)](https://www.hse.gov.uk/work-equipment-machinery/puwer.htm) (not-terms)
- [Lifting Operations and Lifting Equipment Regulations (LOLER)](https://www.hse.gov.uk/work-equipment-machinery/loler.htm) (not-terms)

## Cite or embed

- 2 of 13 equipment record rules read fix a period for keeping the record, newest read 8 November 2026.
- What must be recorded, by rule: the result of an inspection, examination or test 9 of 13, refrigerant or gas leak checks and repairs 2 of 13, a maintenance log or record of repairs 1 of 13, a written procedure, scheme or certification 1 of 13 (13 rules, read 8 November 2026).
- Whose duty it is, by rule: the employer 7 of 13, the owner, user or operator of the equipment or process 4 of 13, the competent person who examines it 1 of 13, not stated 1 of 13 (13 rules, read 8 November 2026).
- How long the record is kept, by rule: no period set in the text 8 of 13, until the next inspection, or for the life of the equipment 3 of 13, a fixed period stated in the text 2 of 13 (13 rules, read 8 November 2026).
- The rule, in its own words, by rule: stated 13 of 13 (13 rules, read 8 November 2026).

Cite as: "What the law makes a plant record about its equipment", updated 2026-11-08, https://sellmaintenancedatatoai.com/datasets/maintenance-records-law/.

CSV: https://sellmaintenancedatatoai.com/datasets/maintenance-records-law.csv
JSON: https://sellmaintenancedatatoai.com/datasets/maintenance-records-law.json
Embed (plain HTML, static link back): see https://sellmaintenancedatatoai.com/datasets/maintenance-records-law/#lead